Checklist

Project Readiness Checklist

Run this in the week before mobilization. A crew standing down on day one because a permit is outstanding costs more than the check would have.

A project readiness checklist confirms a fiber construction project can actually start before a crew mobilizes: locates are current, permits are issued, make-ready is complete, material is on site, access is confirmed, and the traffic control plan is approved.

Before mobilization

  • Sunshine 811 tickets currentLocate tickets placed, marks verified in the field and still within their valid window.
  • Permits issued and on siteFDOT, county or municipal permits in hand, with conditions read and understood.
  • Maintenance of traffic plan approvedMOT plan approved and any lane closure windows confirmed.
  • Make-ready completeFor aerial scope, make-ready work finished and verified rather than assumed.
  • Material on site or scheduledConduit, cable, hardware and vaults confirmed against the take-off.
  • Access confirmedEasements, gate codes, private property permission and staging areas secured.

Coordination

  • Single point of contact named on both sidesWho calls whom when a field condition changes, and what the escalation path is.
  • Pre-construction walkout completedThe route walked with both parties, conflicts noted and resolved on paper.
  • Adjacent trades sequencedAny other contractor whose work must precede or follow, with dates agreed.
  • Reporting expectations agreedWhat the daily report contains, when it arrives and who receives it.

Risk

  • Known conflicts documentedUtilities, structures or conditions likely to require a field decision.
  • Contingency plan for field changesHow a change is priced and approved without stopping the work.
  • Weather and seasonal factors consideredStorm season, water table and any seasonal access limits.

Use your browser print function to save this checklist as a PDF. The print stylesheet strips the navigation and expands everything, so it prints clean. Nothing here is gated and we do not ask for your email to use it.

Request a Bid

Ready to start your next directional drilling or fiber project?

Send the scope and we will come back with a clear, documented bid. Owned crews, aerial and underground under one contract, and a closeout package that lets you close the file.

Most bid requests receive a response within one business day.