The Steps Involved in Aerial Cable Construction
TLDR
An aerial build runs in a fixed order: permits, survey, make-ready, strand, lashing, slack and splicing, then OTDR testing, restoration and a closeout package.
Last updated October 20, 202613 min read
Aerial cable construction follows a fixed sequence: route design and permitting, pole survey and make-ready, messenger strand placement and tensioning, cable placement and lashing, slack storage and splice point setup, fusion splicing with OTDR verification, restoration, then closeout documentation tying every pole to an approved attachment.
What is the order of operations on an aerial build?
Aerial construction is less forgiving of sequence errors than underground work, because every step depends on someone else's approval. A bore can often be redesigned in the field. An attachment cannot be moved up a pole because the crew would prefer it there.
The sequence below is the one that holds on most builds. Where projects go wrong is usually a step performed out of order: cable placed before make-ready cleared, splicing before slack was set, or closeout attempted after the crew demobilized and the field record was never captured.
- Route design, pole line verification and permitting.
- Pole survey and data collection for loading analysis.
- Make-ready engineering and construction, ending in a permit to attach.
- Messenger strand placement, guying, tensioning and bonding.
- Cable placement and the lashing pass.
- Slack storage, splice enclosure placement and risers.
- Fusion splicing and OTDR verification.
- Restoration, cleanup and closeout documentation.
Where are the hold points between steps?
A hold point is a check that has to pass before the next step starts. Aerial builds need them because each step buries the evidence of the one before it. Once cable is lashed, nobody re-checks the strand sag. Once an enclosure is sealed, nobody looks at the slack coil inside the tray again unless a test fails.
The useful hold points are few and specific. Each one has a named check, a person who confirms it, and a record that proves it happened. A hold point with no record is a hope, and it will be the first thing questioned when a pole owner inspection or an acceptance test goes wrong.
Owners benefit from asking for these checks in writing before award. They cost the contractor very little to perform during the build. Reconstructing them afterward is close to impossible, because the condition they verify is hidden by the next step.
| Before this step starts | Confirm that | Record that proves it |
|---|---|---|
| Strand placement | Every pole in the segment has a permit to attach and make-ready is done | Pole list with permit status and field verification photos |
| Lashing | Strand tension and sag match the chart and guys are installed | Dynamometer and midspan readings, guy photos at corners |
| Splicing | Cable jacket is undamaged and slack is stored at the planned locations | Walk-down photos and slack quantities by location |
| Restoration | OTDR and loss results meet the acceptance threshold | Native trace files and the end to end loss report |
| Closeout | Restoration is complete and permits are ready to close | Paired before and after photos and inspection requests |
Step one: route design and permitting
Design starts with a route that is buildable, not just drawable. That means confirming the pole line actually exists as mapped, that spans are within reasonable length for the strand class, and that the route can cross roads, water and railroads at locations where permits are achievable.
Permits stack. Pole attachment applications go to the pole owner. Work in the state right of way needs an FDOT utility permit, and county or municipal rights of way have their own processes. Maintenance of traffic requirements come with those permits and drive crew size and equipment on the day of work.
Design also sets the splice plan: where fiber counts break out, where enclosures land, and where slack has to exist. Deciding that at design time rather than in the field is what keeps splice locations at accessible poles instead of over a canal or in the middle of an intersection.
Step two: survey, make-ready and the permit to attach
The pole survey collects attachment heights, span lengths, guying, midspan clearances and existing violations. Those inputs feed a loading analysis that determines whether each pole can carry the new attachment, and what has to change if it cannot.
Make-ready construction follows: rearranging attachments in the communications space, adding guys and anchors, correcting violations, and replacing poles where the analysis requires it. Existing attachers transfer their facilities on pole replacements, which is normally the longest lead item on the entire project.
Nothing gets attached before the permit issues. The practical discipline is to track status pole by pole and mobilize only into segments where every pole in the segment is cleared, so that a crew never builds into a pole that still has a transfer pending.
Step three: strand placement and tensioning
Strand is pulled span to span, dead ended at terminal poles, and supported at intermediate poles with the specified hardware. Corners and ends of runs get guys and anchors sized for the unbalanced pull, and anchor installation is ground disturbing work, so a Sunshine 811 locate ticket and verified marks come first. Potholing at anchor locations near known services is normal practice rather than an extra.
Tension is then set to the sag target from the sag chart for that strand class, span length and the temperature at the time of stringing. A dynamometer confirms tension during the pull and a midspan measurement confirms the resulting sag and clearance.
Bonding is completed as the strand goes up. Bond connections at poles and to ground rods at the specified intervals are inspection items, and they are far easier to install during the strand pass than to retrofit after cable is lashed.
Step four: cable placement and the lashing pass
Cable is placed by one of two methods. In a block pull, blocks are hung on the strand and the cable is pulled through them from a reel. In a back pull, the cable is paid off at a mid point, figure eighted on the ground to remove twist, and pulled in both directions. Both methods exist to keep the cable inside its rated pulling tension and minimum bend radius.
A pulling swivel between the pulling line and the cable grip prevents rotation from transferring into the cable. Twist in a fiber cable is not always visible and can show up later as added loss, which is why the swivel and the reel brake settings are worth the minute they take.
The lasher then runs the span, wrapping lashing wire in a helix around strand and cable and terminating in a lash clamp at each pole. Cable is inspected for jacket damage before and after the pass, and the lashing wire material is chosen for the setting, which near the coast usually means stainless.
Step five: slack, enclosures and risers
Slack is placed at splice locations, at major crossings, and at transitions to underground, on snowshoes that hold each loop above the fiber minimum bend radius. The sequencing point is that slack goes up before the splicer arrives. A splicer who finds no slack at a planned enclosure either waits or improvises, and improvised slack is where bend loss gets built in.
Splice enclosures are mounted on the strand near the stored slack so a technician can lower the enclosure to a bucket without cutting into adjacent spans. Enclosure position, mounting orientation and drip loops matter in a climate with daily summer rain, since water tracking down a cable into an enclosure is a slow failure mode nobody catches until it causes trouble.
Risers carry the cable down a pole into conduit at transition points. The riser needs mechanical protection, a bend radius that the cable can tolerate at the top and bottom, and stored slack so that the underground portion can be reworked without disturbing the aerial run.
Step six: splicing and OTDR verification
Fusion splicing joins fibers by aligning and arc welding them. A clean splice on matched single mode fiber typically produces very low loss, and the owner's specification sets the per splice acceptance limit, measured bidirectionally. Bidirectional testing matters because a mismatch in fiber backscatter can make the same splice read low from one end and high from the other, producing gainers and false failures.
The full test set on a completed span is normally an OTDR trace from each end at both wavelengths plus an end to end loss measurement with a light source and power meter. The OTDR locates and characterizes events. The power meter verifies the total loss against the link budget. They answer different questions and neither replaces the other.
Splice quality is mostly a preparation problem. Clean strip, clean cleave, clean fusion splicer, and correct sleeve placement produce consistent results. When loss is high on repeated attempts, the cause is usually cleave angle, a dirty V groove or contaminated fiber rather than the splice program.
| Test | What it proves | When it runs |
|---|---|---|
| OTDR bidirectional at 1310 and 1550 nm | Location and loss of each splice, connector and bend event | After splicing each section |
| End to end insertion loss | Total link loss against the design budget | After the link is complete |
| Visual fault locator | Continuity and gross breaks in short spans and inside enclosures | During troubleshooting and fiber identification |
| Connector end face inspection | Contamination or damage on terminated ends | Before mating any connector |
| Midspan clearance verification | The finished run meets required clearances over roads and driveways | After the lashing pass |
Step seven: restoration, cleanup and closeout
Aerial work leaves less ground disturbance than underground work, but it is not zero. Anchor installations, pole holes, riser bores and truck access across grass all require restoration to the standard the permit specifies. Sod, grade and pavement patches get restored to match, and the site gets left clean of wire cuttings, reel debris and hardware packaging.
Closeout is the deliverable most owners actually keep. It should include the as built route with pole identifiers and attachment heights, strand class and hardware, sag or tension verification, slack locations and quantities, splice locations and fiber assignments, OTDR and loss test results, photo documentation, permits and attachment approvals, and the daily production reports from the build.
The reason to build the closeout package during construction rather than after is simple. The information exists on the day the work happens. Reconstructing it weeks later means a return trip and a document that is a reasonable guess rather than a record.
Strilla Communications Company performs aerial cable construction with owned equipment and crews, a single point of contact for daily communication, and closeout documentation delivered as part of the work rather than as an afterthought.
Key takeaways
- Aerial construction runs in a fixed order because each step depends on an approval or a check from the step before it.
- The most common aerial sequencing error is placing cable on poles where make-ready has not actually been completed.
- Every step in an aerial build hides the evidence of the step before it, so each check has to be recorded when it happens.
- Splice acceptance should rest on bidirectional OTDR results plus an end to end loss test, because the two answer different questions.
Key terms
- Back pull
- A cable placement method where the reel is set at a midpoint, cable is pulled one way, then the remaining cable is laid on the ground in a figure eight and pulled the other way. The figure eight removes twist before the second pull.
- Riser
- The protected run of cable from an aerial span down a pole and into underground conduit. A riser needs a guard or conduit against damage, a bend the cable can tolerate at top and bottom, and stored slack on both sides of the transition.
- Dynamometer
- A tension meter placed in line with the strand or pulling line during installation. It shows the actual pulling force, so crews can match strand tension to the sag chart and keep fiber cable below its rated maximum pulling tension.
- Hold point
- A planned check in a construction sequence that must pass, and be recorded, before the next step begins. On aerial builds, typical hold points include permit status before strand, sag before lashing, and test results before restoration and closeout.
| Step | Main output | Record kept for closeout |
|---|---|---|
| Design and permitting | Buildable route and splice plan | Approved permits and the issued design set |
| Survey and make-ready | Space on every pole and a permit to attach | Pole list by owner tag with permit references |
| Strand placement | Tensioned, guyed and bonded strand | Sag and tension readings, guy and bond photos |
| Cable and lashing | Cable bound to strand span by span | Placement notes and jacket inspection photos |
| Slack, enclosures, risers | Repair capacity and transitions in place | Slack quantities and enclosure locations |
| Splicing and testing | Continuous, verified fiber path | Splice records, native OTDR files, loss results |
| Restoration and closeout | Site returned to permit standard | Paired photos, inspection results, as-builts |
What this means for your project
Most aerial schedule losses come from sequence breaks, not slow crews. A crew sent to a segment where one pole still has a pending transfer, or a splicer sent out before slack was stored, loses the day and usually needs a return trip. Ask your contractor how they confirm readiness before each mobilization, and expect an answer that names records rather than habits.
Cost and documentation risk travel together. Hold points that are checked and photographed during the build cost little and make the closeout package a matter of assembly. Hold points skipped during the build show up later as disputed clearances, failed acceptance tests or a remobilization to gather missing data. Write the hold points and their records into the contract, and tie part of the final payment to receiving them.
Related reading
- Aerial cable construction servicesThe full aerial scope, from strand and lash to pole attachment support.
- Aerial fiber placementHow fiber is pulled and placed on strand without damage.
- Fusion splicing and testingSplicing practices and the OTDR testing that proves the work.
- What strand and lash really involvesA closer look at strand, sag, lashing and slack on each span.
- During constructionHow daily reporting and field checks work while crews are building.
- Closeout checklistA checklist for confirming every closeout record is in hand.
Frequently Asked Questions
- How long does an aerial fiber build take compared with underground?
- The construction itself is usually faster aerially, because there is no excavation, no spoil handling and less restoration. The total schedule often is not, because make-ready and permitting sit ahead of construction and depend on pole owners and existing attachers. On routes where poles already have space, aerial is the fastest path. On routes needing pole replacements, underground can finish sooner.
- Do aerial jobs require a Sunshine 811 locate ticket?
- Yes, for any ground disturbing portion. Anchor installation, pole setting and riser bores all require a locate ticket with marks verified before work begins. Anchors are a common strike location because they get driven at an angle into ground that was never scanned for the aerial route, so potholing near known services is a sensible precaution.
- What splice loss is acceptable on a new aerial build?
- Whatever the owner's specification says, and it should be written down before splicing starts. Specifications usually set a maximum loss per fusion splice, measured bidirectionally on an OTDR, plus a total link limit verified with an end to end loss test against the design budget. Clean single mode splices normally land well under typical limits, so consistently high readings point to preparation or handling problems.
- What should be in an aerial closeout package?
- As built route with pole identifiers and attachment heights, strand class and hardware, sag or tension verification, slack storage locations, splice locations and fiber assignments, bidirectional OTDR traces and end to end loss results, photo documentation of attachments and guying, permits and attachment approvals, and daily production reports covering the build.
- Does weather stop aerial construction in Florida?
- Lightning and high wind do. Crews come down from buckets when lightning is in the area, and aerial lift work stops when wind makes it unsafe. Central Florida summer afternoons often bring thunderstorms, so aerial crews tend to schedule bucket work early in the day. During hurricane season, active builds should have a plan for securing reels, partially lashed spans and open enclosures before a storm arrives.
- Can strand and cable go up on the same day?
- Sometimes, on short segments where the strand can be tensioned, guyed and checked before the cable crew arrives. On longer routes, strand usually runs ahead of the cable crew by at least a segment. That gap leaves time to verify sag and guying before lashing locks the strand in place. Rushing the cable onto unchecked strand is a common source of rework at corners and dead ends.
- Who inspects an aerial build after it is finished?
- Usually several parties. The pole owner may run a post construction inspection to confirm attachment heights, clearances and hardware. The agency that issued the right of way permit inspects restoration and traffic related work. The network owner's inspector or engineer reviews test results and the closeout package before acceptance. Each inspection goes faster when the contractor's photos and as-built data are already organized by pole tag.
Related services
- Aerial Cable ConstructionPole line construction, strand placement, lashing, and aerial fiber installation with make-ready coordination and NESC clearance verification.
- Strand and LashStrand and lash aerial cable construction in Central Florida: messenger strand framing, tensioning to sag, machine lashing, and clearance checks.
- Aerial Fiber PlacementAerial fiber placement in Central Florida: lashed loose tube, figure-8, and ADSS cable placed with tension control and planned slack storage.
- Fiber Splicing & InstallationFusion splicing, fiber placement, termination, and enclosure installation with bidirectional OTDR support and a recorded loss value for every fiber.
- As-Built DocumentationAccurate as-built records captured in the field during construction, not reconstructed afterward. Coordinates, depths, photos and reconciled footage.
Request a Bid
Ready to start your next directional drilling or fiber project?
Send the scope and we will come back with a clear, documented bid. Owned crews, aerial and underground under one contract, and a closeout package that lets you close the file.
Most bid requests receive a response within one business day.